The question behind the question
When a managing director, a CIO or a product owner asks whether their project should be agile or waterfall, they are not really asking about methodology. They want to know how much of their team's time it will take, when they will see something that works, how they will keep the budget under control and what exactly they will sign off at the end.
This article answers those questions. It does not try to sell agile: both approaches have real strengths and real weaknesses, and most bespoke software projects that go well borrow from both.
Two logics, not two religions
The V-model: decide everything, then build everything
The V-model, the structured form of waterfall that French buyers know as the "cycle en V", splits the project into successive phases. You go down the left branch first: statement of needs, requirements specification, functional specification, technical design. Then comes development. Then you climb the right branch, where each test level answers one specification level: unit tests, integration tests, validation, user acceptance.
The logic is contractual as much as technical. The business side describes what it wants, the supplier commits to a scope, a price and a date, and final acceptance checks that the delivery conforms to what was written.
Agile: decide as you go, with evidence
Agile methods start from the opposite observation: on new software, nobody can describe everything upfront, and what you learn from seeing the product work is worth more than what you imagined on paper. So the project moves in short iterations of a few weeks, each delivering a usable piece of the software.
The founding text is the 2001 Agile Manifesto. It fits in four values, and the one that most changes the relationship with a supplier is "customer collaboration over contract negotiation". The manifesto states that the items on the right still have value. Agile does not remove the contract, the documentation or the plan; it ranks them below working software. The twelve principles behind it ask teams, among other things, to welcome changing requirements even late in development.
Agile is a family of practices, not a single method. Scrum and Kanban are its two most widespread frameworks; we compare them in Scrum or Kanban for a bespoke software project.
What actually changes for you as the client
Your involvement
With the V-model, your effort is concentrated at both ends: a lot of work at the start to write and approve the requirements and specifications, and a lot at the end for acceptance testing. In between, you follow progress through a steering committee without being called on day to day.
With agile, the effort at any given moment is lower, but it never stops. You need someone who knows the business, who has the authority to decide and who is available every week to clarify needs, settle priorities and approve what is delivered. This is a frequent cause of failure on the client side of agile projects: agile is chosen for its flexibility, then nobody is freed up to feed it.
Your visibility
With the V-model, progress is measured in documents and milestones: specifications approved, design complete, development "80% done". The first screen you can really use arrives late, and that is often when misunderstandings surface.
With agile, you see working software at the end of every iteration. A delay or a misunderstanding shows up within weeks instead of months. The trade-off is a less reassuring overall picture at the start: there is no single document describing everything you will have at the end.
Your budget
This is where most of the received ideas live.
The V-model goes naturally with a fixed-price contract: fixed scope, fixed price, fixed deadline. The price is known at signature, which reassures a finance director. But that price includes a risk margin, and every change in requirements along the way goes through a change request, with its own negotiation and delay. A frozen scope only protects the budget if the need does not move.
Agile swaps the adjustment variable. Budget and calendar are fixed, and scope adapts: features are ranked by value, the most important are delivered first, and at each iteration you decide to continue, change direction or stop. The contract then takes the form of time and materials, often capped, or a fixed price per batch. You control the spend, but at signature you do not know the exact feature list you will get for it.
Neither approach makes a project cheaper by nature. They put the risk in different places. The contractual side is covered in our article on fixed price vs time and materials.
Your acceptance testing
With the V-model, acceptance is a phase of its own at the end of the project, with a test plan, defects graded by severity and a signed acceptance report that usually triggers the final invoice and the start of the warranty period. It is legally clear, but you discover the whole software at once, at a point where fixing things is expensive.
With agile, acceptance is continuous: each feature is validated as it arrives, against acceptance criteria defined before development. The workload is spread out and gaps are fixed early. The risk is approving pieces without ever testing the whole. On a serious project you therefore keep an end-to-end acceptance run before every production release.
V-model and agile: pros and cons
| Criterion | V-model | Agile |
|---|---|---|
| Requirements | Fully described before starting | Refined and prioritised continuously |
| Supplier commitment | Scope, price and deadline | Resources, quality and delivery cadence |
| Typical contract | Fixed price | Capped time and materials, or fixed price per batch |
| Client involvement | Heavy at the start and the end | Steady, every week |
| First usable version | End of project | From the first iterations |
| Change in requirements | Change request | Reordering of priorities |
| Acceptance | One formal final phase | Continuous, plus an end-to-end run |
| Main risk | Delivering to spec but beside the need | Drifting without decisions or a clear direction |
| Documentation | Produced upfront, exhaustive | Produced along the way, targeted |
When the V-model is still the right call
The V-model is not an obsolete method. It remains a good fit in several situations.
- Fixed regulatory scope. When the software must apply a standard, a mandated exchange format or a calculation rule set by law, the need is not something you discover along the way. Specifying it once is more efficient.
- Public tenders with a technical specification. In French public procurement, for instance, a technical specification document (the CCTP) describes the need before the tender, and bidders answer with a price and a deadline. The structure of the tender pushes towards a commitment on results, even if nothing prevents the delivery from being organised in batches afterwards.
- Traceability requirements. In fields where every requirement must be linked to a test and to evidence, the mapping between the two branches of the V is exactly what the auditor asks for.
- An unavailable client. If nobody on your side can give the project time every week, a good requirements specification beats an agile project with no counterpart.
Conversely, the V-model is risky as soon as the product is new, users have not yet been consulted, or the market may shift during the project.
What you are rarely told about agile
Agile has its own failure modes. Without an overall vision, features pile up without coherence. Without a decision-maker on the client side, the backlog turns into a wish list. Without technical discipline (automated tests, continuous integration, code review), the speed of the first iterations is paid back as debt a few months later. And "we are agile" is sometimes an excuse for documenting nothing and estimating nothing.
A well-run agile project is no less rigorous than a V-model one. The rigour is applied to different things.
The hybrid approach: scoping, then iterative delivery
In practice, many bespoke software projects for small and mid-sized companies run in two stages.
A short scoping phase, with fixed scope and price. A few weeks of workshops with the business teams to clarify objectives, map processes, identify constraints (regulation, security, existing systems to interface with) and choose the architecture. You come out with a scope that is broken down and prioritised, a budget estimate per batch and a path to production. This deliverable plays the role of a requirements specification, in a lighter form, and it belongs to you.
Iterative delivery, within an envelope. Development moves in iterations of two to three weeks, with a demo at the end of each. A steering committee, usually monthly, tracks three things: budget spent, scope delivered and work remaining. It makes the heavy trade-off decisions.
Contractual milestones kept in place. Each production release is preceded by an end-to-end acceptance run and a signed report. You keep the V-model's reference points where they are useful, namely the budget commitment and formal sign-off, without freezing functional detail eighteen months ahead.
This is the organisation we recommend most often for bespoke software. Our services page describes what we cover, from scoping to operations.
Quick decision guide
Lean towards the V-model if:
- the need is stable, known and already written down;
- a regulation or a tender specification fixes the scope;
- you need a firm price before starting anything;
- your teams will not be available during the build.
Lean towards agile if:
- the product is new or the need is still uncertain;
- you want a first version in service quickly, even if it is enriched later;
- someone on your side can make decisions every week;
- you would rather steer a budget than a feature list.
Choose a hybrid approach if you recognise yourself in both lists, which is the most common case.
Conclusion
The choice between agile and the V-model depends on how stable your need is, how available you are and where you prefer to place the risk. The useful question to ask a supplier is therefore less "are you agile?" than "how will I track my budget, see progress and approve what you deliver?".
To scope a bespoke software project or get an opinion on the organisation that fits it best, email us at contact@your-digital-hub.com or see our services. You can also describe your project on our contact page.