Custom software development cost: how the price is built

12 min read

Cover — Custom software development cost, how the price is built

The short answer

The price of custom software is an amount of work, expressed in person-days, multiplied by a daily rate, profile by profile, plus a contingency for unknowns. There is no list price, because the effort depends on your scope: number of roles and screens, business rules, integrations, data migration, security and performance requirements.

This article therefore gives no "average price", which would tell you nothing about your project. It explains how a quote is built, so that you can read, compare and negotiate the ones you receive. It reflects practice in France, where suppliers quote in person-days (jours-homme) and daily rates (TJM, for taux journalier moyen).

The formula: effort multiplied by a rate

Every development quote, however it is presented, rests on the same sum:

Price = sum, per profile, of (estimated days x daily rate of the profile)
      + contingency
      + any external costs (licences, third-party services)

A person-day is one day of work by one person. The effort of a project is the total of those days, not to be confused with duration: one hundred days of effort are delivered in five months by one person or in ten weeks by two, plus coordination.

The daily rate varies by profile: developer, technical lead or architect, UX/UI designer, tester, project manager, DevOps engineer.

What a daily rate contains

A software company's daily rate does not only pay the salary of the person assigned. It also covers social contributions, non-billable days (leave, training, pre-sales), technical supervision, development tools and infrastructure, insurance, support functions and margin.

This is why the freelance rate surveys that are often quoted are not directly comparable: they measure the price of one person alone, without supervision, without continuity during absences and without a team commitment. We do not publish a market range here: the figures in circulation vary widely by source, region, technology and seniority, and none of them tells you what your project will cost.

Above all, a daily rate is never compared on its own. A more expensive senior profile who builds a feature in three days costs less than a junior who takes six and leaves defects to fix.

The cost drivers

Driver Why it weighs Questions to ask yourself
Functional scope Each feature is designed, built and tested What is essential in the first version?
Roles and permissions Each role multiplies the cases to handle and test How many profiles, with what real differences?
Number and complexity of screens A rich input screen is worth several read-only screens Which screens carry business rules?
Business rules Calculations, approval flows and special cases concentrate the effort Are they written, stable, known to all?
Integrations Dependence on third-party systems, often poorly documented Do the APIs exist? Who answers questions?
Data migration Cleaning, mapping, migration rehearsals What volume, what quality, how many sources?
Non-functional requirements Security, performance, availability, accessibility What level is really needed?
Design Existing brand or identity to create, user research Do you start from a design system?
Testing and quality Automated tests, acceptance, audits How long will this software live?
Project management Scoping, workshops, steering committees, documentation How many stakeholders and approval levels?

Two remarks. Integrations and data migration are the items most often underestimated, because they depend on things neither you nor the supplier fully control. And non-functional requirements, absent from many requests, can change the architecture and therefore the price. A structured requirements specification deals with these points before you consult.

For a rebuild, the state of the existing code becomes a driver in its own right. A prior code and security audit tells you what can be reused before a legacy application modernization is priced.

How an estimate is produced

1. Break down

The scope is split into work packages, then into features small enough to be estimated one by one. A line reading "order management: 40 days" is not an estimate, it is an intuition. The same line split into creation, modification, cancellation, statuses, notifications and export becomes verifiable.

2. Estimate with three points

For each item, the estimator gives three values: optimistic (O), most likely (M), pessimistic (P). The classic PERT formula derives a weighted value:

Estimate = (O + 4 x M + P) / 6

The benefit is not arithmetic precision. It is to make uncertainty visible: a wide gap between O and P signals a poorly understood topic, hence a question to ask or an assumption to write down.

3. Add cross-cutting activities

Development is only part of the effort. Add scoping, UX/UI design, architecture, testing and acceptance, environment and deployment setup, project management, documentation and warranty.

4. Write the assumptions and provide for risks

Every estimate rests on assumptions: "the ERP API is documented", "data is supplied clean", "a single approval level". They should appear in the quote. A contingency covers the identified risks.

Uncertainty narrows with scoping

An estimate made from a two-page idea is necessarily wide. The cone of uncertainty model, popularised by Steve McConnell after Barry Boehm's work, states that an estimate produced at the initial concept stage can differ from the final outcome by a factor of four, in either direction, and that the gap narrows as decisions are made.

In practice: ask for a range before scoping and a commitment after it. A firm price given on a vague need contains either a large contingency or a future change request.

Worked example (fictional figures)

The following example illustrates the method. The efforts, coefficients and contingency are invented for the demonstration: they are neither market prices nor reference ratios. It uses the fictional work-order management application from our requirements specification template.

Step 1: three-point estimate of development

Work package O M P (O + 4M + P) / 6
Foundation, authentication, roles 8 12 20 12.7
Request management 15 22 35 23.0
Planning and assignment 10 16 30 17.3
Technician mobile interface 12 18 30 19.0
ERP interface 6 10 26 12.0
Data migration 4 7 16 8.0
Dashboard and exports 5 8 14 8.5
Total (days) 60 93 171 100.5

The ERP interface has a pessimistic value that is high compared with its most likely value: a sign of an uncertainty to resolve during scoping, for example by testing the API.

Step 2: cross-cutting activities and weighting by profile

Instead of euros, the example uses a coefficient per profile, relative to a base rate. The budget is obtained by multiplying the weighted total by that base rate.

Activity Days Profile coefficient Weighted days
Scoping 8 1.2 9.6
UX/UI design 12 1.0 12.0
Architecture and technical lead 10 1.3 13.0
Development 100.5 1.0 100.5
Testing and acceptance 15 0.9 13.5
Go-live 6 1.1 6.6
Project management 14 1.2 16.8
Total 165.5 172.0

Step 3: contingency and result

With a 10% contingency (a fictional value), the total rises from 172.0 to 189.2 weighted days.

Build budget = 189.2 x base daily rate

The calculation shows three things you can check on a real quote: pure development is only part of the effort (here 100.5 days out of 165.5), uncertain packages are spotted by the gap between O and P, and each line can be discussed separately.

Costs after delivery

The build price is not the cost of the software. Over its life, you need to count the total cost of ownership, which includes:

  • Hosting and cloud services: servers, database, storage, backups, monitoring. The amount depends on architecture and traffic; ask for a monthly estimate in the quote.
  • Corrective maintenance: fixing defects found in use, after the warranty period.
  • Preventive and security maintenance: upgrades of the language, framework and dependencies, vulnerability fixes. Software that is not updated gradually becomes costly to change and risky to expose.
  • Enhancements: new features, regulatory or business adaptations.
  • Licences and third-party services: email and SMS delivery, maps, payment, monitoring tools.
  • Support and operations: on-call cover if any, user assistance, administration.
  • Your internal costs: time of the product owner, of users during acceptance, training.

Ask for the proposal to price at least the first year of operation.

Fixed price or time and materials: the effect on price

The contract model does not change the real effort, but it changes who carries the risk, and therefore how the price is presented. French suppliers offer three models.

  • Fixed price (forfait): the supplier commits to a price for a scope. It builds in a risk contingency, which you pay whether the risk materialises or not, and any change goes through a change request.
  • Time and materials (régie): you pay for time spent. There is no hidden contingency, but no ceiling either if you do not steer.
  • Agile fixed price (forfait agile): the budget is capped and the scope is adjusted by prioritisation.

These models, and the clauses to include, are detailed in our article on fixed price, time and materials and agile contracts in France.

Reducing the budget without reducing quality

Negotiating the daily rate has a limited effect. The real levers act on the effort.

  1. Define an MVP. In the example, deferring the technician mobile interface and the dashboard removes 27.5 days of development, plus a share of testing and design. The first version is useful sooner, and feedback from use guides what follows.
  2. Really prioritise. Sort features into must, should and could. The "could" items become an optional tranche priced separately.
  3. Simplify business rules. A special case that concerns a few records a year can stay manual.
  4. Reuse. Proven open source components, standard services for authentication, payment or messaging, an existing design system.
  5. Prepare your data. Cleaning done in-house before migration shrinks a highly uncertain item.
  6. Resolve unknowns early. A scoping phase or a technical prototype on the riskiest integration tightens the estimate, and so the contingency.

What should not be cut: testing, security and operations documentation. The saving comes back, larger, in maintenance costs.

Comparing quotes

Large gaps between proposals rarely come from the rate. They come from different assumptions. Before comparing totals, check:

  • Is the scope covered the same, feature by feature?
  • Are assumptions and exclusions written down?
  • Is the effort detailed by work package and by profile?
  • Are testing, acceptance, go-live and project management included?
  • Are data migration and interfaces priced?
  • Who is on the team, with what seniority?
  • What warranty after acceptance, and for how long?
  • Are code ownership and reversibility provided for?
  • Are hosting and maintenance costs estimated?

A French public scheme worth knowing: the innovation tax credit

If your company is taxed in France and the software is a new product intended for the market, part of the spending may fall under the crédit d'impôt innovation (CII). According to the official government page, verified on 20 February 2026, it is reserved for small and medium-sized enterprises, covers the design of prototypes or pilot installations of new products, amounts to 20% of eligible expenses in mainland France within a ceiling of 400,000 euros of expenses, and applies to expenses incurred until 31 December 2027. The page states that a digital solution such as a SaaS platform can be eligible if it is a new product, not yet on the market and superior to existing ones; an innovative service, a new organisation or a simple update of an existing offer is not. Eligibility is assessed case by case: confirm it with your accountant before including the credit in your financing plan.

Frequently asked questions

How much does custom software cost?

The cost equals the effort in person-days multiplied by the daily rates of the profiles involved, plus a contingency. The effort depends on scope, integrations, data to migrate and security and performance requirements. Without those elements, any figure quoted is a guess.

How much does it cost to develop a web application?

The method is the same as for any software: breakdown into features, estimate of each, plus design, testing and project management. The items that move the result most are the number of roles, the business rules and the connections to other systems.

How do you estimate the effort of a software project?

Split the scope into items of a few days, estimate each with three points (optimistic, most likely, pessimistic), apply the formula (O + 4M + P) / 6, add cross-cutting activities and then a risk contingency. Write down the assumptions used.

Why are two quotes for the same project so different?

Because they do not price the same project. The gaps come from the scope as understood, the assumptions, the items included or not (testing, data migration, go-live) and the seniority of the team, far more than from the daily rate.

Conclusion

The price of custom software is not a mystery: it is an effort, rates and a contingency, each open to discussion line by line. Your best lever is not negotiating the daily rate; it is the clarity of the need, prioritisation and reducing unknowns before signing. And the right figure to compare is not the build cost, but the total cost over the life of the software.

To obtain a reasoned estimate for your project, write to us at contact@your-digital-hub.com or see our services, from scoping to operations. You can also describe your software project on our contact page.

Let's talk about your project. Send us the essentials.

Tell us the context, whether it is a new build, a takeover or a migration, the technologies in place and your target date.